The Alba project continues with the construction of the deep foundations, with the reinforcement and preparation of templates for installing the piles, the preparation for the pouring of the cisterns and machine room continues, the pouring of the basement slab and the pouring of the perimeter wall is being prepared; 200 mt2 of slab and a part of the perimeter wall have already been poured.

Also, progress is being made with the casting of micropiles and the preparation for the casting of the micropile crown.

The placement of installations for pluvial drainage and for the physical soil network has begun, leaving preparations of steps in cistern walls and foundation slab.