We continue with Stage 1 of Alba Marina Puerto Cancun where the following has been achieved:
- 2,500 m3 of material has been dug.
- Preliminary drilling has begun for the driving of the deep foundation, based on prefabricated reinforced concrete piles with foundation, based on prefabricated reinforced concrete piles with different sections.
- Progress in drilling and construction of micropiles.
- In addition to having two drills for piles and one for micropiles, we have safety personnel, a topography brigade, and implementation of a rigorous hygiene plan.