Construction progress September 20th, 2021

The Alba project continues with the construction of the deep foundations, with the reinforcement and preparation of templates for installing the piles, the preparation for the pouring of the cisterns and machine room continues, the pouring of the basement slab and the pouring of the perimeter wall is being prepared; 200 mt2 of slab and […]

Construction progress report August 27, 2021

We continue with Stage 1 of Alba Marina Puerto Cancun where the following has been achieved: 2,500 m3 of material has been dug. Preliminary drilling has begun for the driving of the deep foundation, based on prefabricated reinforced concrete piles with foundation, based on prefabricated reinforced concrete piles with different sections. Progress in drilling and […]

Construction progress report August 11th, 2021

The construction of Alba Marina Puerto Cancun has begun, in the so-called Stage I, 2,500 m3 of material have been dug and preliminary drilling has begun for the driving of the deep foundation based on prefabricated reinforced concrete piles with different sections according to the project and lengths ranging from 6 to 15 m., as […]